Concrete pours into Michigan physics site

|
Photo - Workers pour concrete Wednesday, July 23, 2014, at Michigan State University's Facility for Rare Isotope Beams in Ann Arbor, Mich. The $730 million research facility known as FRIB is funded by the Department of Energy Office of Science, Michigan State University and the State of Michigan. About 1,400 cubic yards of concrete will be poured Wednesday for a portion of a tunnel floor for the facility's superconducting linear accelerator. (AP Photo/The State Journal, Greg DeRuiter) NO SALES
Workers pour concrete Wednesday, July 23, 2014, at Michigan State University's Facility for Rare Isotope Beams in Ann Arbor, Mich. The $730 million research facility known as FRIB is funded by the Department of Energy Office of Science, Michigan State University and the State of Michigan. About 1,400 cubic yards of concrete will be poured Wednesday for a portion of a tunnel floor for the facility's superconducting linear accelerator. (AP Photo/The State Journal, Greg DeRuiter) NO SALES
News,Business

EAST LANSING, Mich. (AP) — The construction of a new national facility for nuclear science at Michigan State University is continuing with the addition of 140 truckloads of concrete.

About 1,400 cubic yards of concrete was being poured Wednesday for a portion of a tunnel floor in what will be the school's Facility for Rare Isotope Beams, The Lansing State Journal (http://on.lsj.com/1mCmPBN ) reported. The tunnel will hold the facility's superconducting linear accelerator, which will produce beams of subatomic particles traveling at half the speed of light.

Reid Goniwiecha, regional sales manager for Superior Materials LLC, said it will take 19 trucks about eight hours to do the job.

He said crews will need to complete four more concrete pours just to finish the floor of the tunnel. The next pour will take place in a couple of weeks, after the area has been waterproofed and reinforced with steel.

The $730 million research facility known as FRIB is funded by the Department of Energy Office of Science, Michigan State University and the State of Michigan. The university won a national competition to host the project in 2008.

The 227,000 square foot building is expected to open sometime between 2020 and 2022.

___

Information from: Lansing State Journal, http://www.lansingstatejournal.com