WLUC-TV reports (http://bit.ly/YxLCdP ) that workers at the Marquette County mine plan to launch the 3.5-ton drill bit on Wednesday that works inside the mine up to the surface. It's being assembled underground.
Mine officials say they created a similar hole last month for air intake and emergency access. The second is for exhaust.
Three men will work the drill — one of the few in North America — from the surface.
Company officials said last week they'll delay the start of nickel and copper production because of the economic situation and volatile commodities markets. Construction is about 80 percent complete.
___
Information from: WLUC-TV, http://www.wluctv6.com